Cycleway 9 – Chiswick High Road Construction of changes to Temporary Scheme

Construction

Hounslow Highways have been carrying out construction on behalf of Transport for London and LB Hounslow. The works to implement changes to Cycleway 9 on Chiswick High Road, between Goldhawk Road and Chiswick Lane began on site from Monday 22 November 2021, with the aim of completing construction by Spring/Summer 2022.

The delivery of the scheme has been split into phases in order to ensure the scheme is delivered effectively with as little disruption to the local transport infrastructure as possible.  Please see our construction timetable below:

Phase

Works Location (within Chiswick High Road unless stated)

Estimated Start Date

Estimated Duration

1A

Chiswick Lane Junction - North Footway

Wed 24/11/21

Completed

1A

Chiswick Road North Footway - 58 to 72

Mon 06/12/21

Completed

3A

Netheravon Road to Airedale Avenue

Mon 20/12/21

Completed

4A

Airedale Avenue to Homefield Road

Tue 04/01/22

Completed

3B

Netheravon Road to Airedale Avenue

Mon 17/01/22

Completed

4B

Airedale Avenue to Homefield Road

Mon 17/01/22

Completed

5

Airedale Avenue to 73 Chiswick Road

Mon 24/01/22

Completed

1B

Flats Crossovers OR Power House and Restaurant Crossover?

Mon 31/01/22

Completed

Raised table 2

Netheravon Road

Wed 02/02/22

Completed

1B

Power House Crossover

Mon 07/02/22

Completed

6

Chiswick Lane Junction - South Footway

Mon 14/02/22

Completed

Raised table 3

Airdale Avenue

Mon 14/02/22

Completed

N/A

Arrival of granite kerbs and cycle delineators on site

Mon 14/02/22

Completed

2

Chiswick Road - South Footway 15 to Netheravon Road

Mon 21/02/22

Completed

Raised table 4

Homefield Road

Mon 21/02/22

Completed

Raised table 1

Access to properties for 19 & 23 Chiswick High Road

Mon 07/03/22

Completed

8

British Grove Junction - South Footway

Wed 16/03/22

Completed

N/A

BT Works on British Grove Road

Mon 28/03/22

Completed

Resurfacing

Resurfacing, Anti-skid, Lining - night work

Sun 10/04/22

Completed

9

British Grove Junction - North Footway

Mon 11/04/22

Completed

N/A

Commissioning of Bus Garage Signals

Wed 04/05/22

Completed

Raised Table X

Construct British Grove Road

Mon 30/05/22

Completed

Resurfacing

Resurfacing of Goldhawk Road Junction

Fri 03/06/22

Completed

7

British Grove Junction - South Footway

Mon 09/05/22

Tue 07/06/22

Raised Table 5

St Peter's Square

Mon 13/06/22

Fri 24/06/22

N/A

HH & LBH&F New Lighting Column works

Tue 28/06/2022

Wed 29/06/22

N/A

Commissioning of route signals

TBC

Fri 08/07/22

Please bear in mind that the supplied dates are subject to change as the scheme progresses.

Throughout construction households on the effected streets have received construction notification letters in advance to inform them of any upcoming works. Once the completion date is confirmed additional notification letters will be sent out to residents in the vicinity of Chiswick High Road. Additional notification will be sent out should there be any changes to the completion date.

Traffic signal issues

During this construction, if you notice any prolonged, or serous signal permanent failures that are causing disruption, please visit our Traffic Lights web page to report the faults.

If the issue is with a temporary signal, please report it to traffic@hounslow.gov.uk, where a member of the team will pass on your enquiry to Hounslow Highways.